ExamPlay Dark Logo
Conectare

JAMB - Mathematics (1979 - No. 29)

12 men complete a job in 9 days. How many men working t the same rate would be required to complete the job in 6 days?
24
18
12
9
8

Explicaţie

12 men in 9 days,

1 day in \(12 \times 9\) men

In 6 days we have \(\frac{12 \times 9}{6}\) men

= \(\frac{108}{6}\)

= 18 men

Comentarii (0)

Autentifică-te pentru a comenta
Publicitate
BrainBehindX Inc Logo
©2026; Cu sprijinul BrainBehindX Inc