WAEC - Physics (2000 - No. 14)

Using the force displacement diagram shown above. Calculate the work done

2000J
1000J
20J
5J

Обяснение

Work done = area under the triangle

Work done = \(\frac{1}{2}\) x base x height = 0.5 x 20 x 100 = 1000J

Therefore, the work done, as calculated from the force-displacement diagram, is 1000J